Client:  Whittens 

Site:  FMG Iron Bridge (CHF) 

Service:  E&I Installation & Commissioning 

Scope:  Installation of 1.5km of 22KV HV Cable & Terminations 

Value:  $584,000 

Coastal Electrics Installed 1.5km of 22kV HV cabling and fibre optic cabling from the Concentrate Handling Facility (CHF) to the Concentrate Diversion Pond (CDP), this included the installation and commissioning of one HV transformer, Kiosk Substation, multiple field instruments and pumps. 